Home renovation works

How a renovation project works, from the start to the works

A renovation project turns your ideas into decisions made before the works begin: what is kept, what is demolished, which materials are used and how each task is carried out. It goes through the survey, the concept design, the detail design and the tendering to building contractors. That way, the proposals are comparable and the works bring fewer surprises.

By Sofia Silva30 August 20196 min read

How a renovation project works, from the start to the works

In short

  • The renovation project organises the decisions before the works, so that the building contractors' proposals can be compared on an equal footing.
  • It starts with the Client's needs and an accurate on-site survey, and only then moves on to design.
  • The concept design (layout of the spaces, materials and 3D images) guides the whole project: it is the stage in which the Client should take part most.
  • The detail design and the bill of quantities (mapa de trabalhos e quantidades) make it possible to request specific proposals.
  • The Client hires the building contractors directly; spacelovers designs and provides technical assistance during construction.

Why should a renovation start with a design?

Renovating a house, an apartment, an office or a commercial space means deciding many things at the same time. Without a design, those decisions are made during the works, when changes cost more and complicate coordination between trades.

spacelovers' interior renovations are always preceded by a design. Defining the works, the materials and how they fit with what already exists allows the building contractor to plan the works with complete information. To find out when to involve an architect, read when to hire an architect.

If you are still weighing up whether it is worthwhile, see whether it is worth buying an old house to restore, which also compares buying another house with renovating your current one. Find out about interior renovation and apartment renovation.

Survey and diagnosis: how does the project start?

Identifying the Client's needs

Before the first meeting, we ask the Client for the floor plan of the property, if they have one. It helps the architect prepare and give better advice.

After the first contact, a visit to the property and a meeting are arranged, at which the broad lines of the intervention are recorded. It can be useful to send photos of examples you like: they help translate your taste into the design of the proposals.

How to prepare for the first visit?

A well-prepared visit makes the conversation more useful. Before it, have to hand:

  • Two lists: what is essential and what is desirable.
  • An investment ceiling: stating it from the outset makes it possible to propose solutions that fit within it. For a first reference, use the renovation cost simulator.
  • Drawings or sketches, even simple ones, if you have them.
  • When you would like to carry out the works, to confirm later with the building contractor.
  • The condominium rules for works inside the units, such as the permitted hours.

Also make sure there is access to all spaces, including storerooms, the attic or the basement, and be present to answer questions on the spot.

Accurate on-site survey

The space is analysed in detail to identify the key points of the project:

  • the load-bearing structure (columns, beams and load-bearing walls);
  • the vertical risers and supply risers;
  • the ventilation and ducts;
  • the location of the electrical panels and meters.

The measured survey is carried out with equipment for measuring distances and angles. The floor plan of the existing space, the relevant heights, the recesses and the characteristic elements are recorded. See how the on-site survey is carried out.

At this stage, the visible construction defects are also identified, so that their repair is described in the works.

Consulting the file in the municipal archive

When the complexity of the works requires it, or there are doubts about the building's construction system, the property's file is consulted in the municipal archive. It provides specific information about the building and supports the proposed intervention.

Concept design and choices: where is the project decided?

Layout of the spaces

Renovation often involves redefining the spaces. Changes to the floor plan are studied: walls to be demolished and built, changes to openings and opening systems, the new layout of the kitchen, cabinets, pantries, wardrobes and bathroom furniture.

This stage guides the whole project from then on. That is why it is the one in which you should take part most.

Schedule of materials and equipment

The schedule of materials brings together, for each space, the proposals for finishes and equipment: sanitaryware, taps, sinks, among others. It serves as the basis for the Client's choices and, later, for the specifications of the detail design.

3D images

The 3D images show the spaces with the chosen materials and the layout already discussed. They give a realistic idea of the result and allow adjustments to be made where needed, until the project is to your liking.

Choosing the proposal and revision

After choosing the proposal, it is natural for some details to need revising. This adjustment is made before moving on to the next stage, where everything is specified. See the stages of an interior renovation project.

Detail design and engineering specialties: what does it contain?

The detail design translates the decisions into drawings and documents that a building contractor can price and carry out. It usually includes:

  • alterations plan, with demolitions and new construction (the "reds and yellows", vermelhos e amarelos);
  • dimensioned plan;
  • plans of the technical networks, such as electricity (sockets, switches and panel);
  • drawings of fitted furniture: kitchen, bathrooms and built-in wardrobes;
  • schedule of openings and interior elevations;
  • bill of quantities.

When the renovation affects the installations or the structure, the engineering specialty projects are added, coordinated by the studio with the architecture. Find out more about the detail design and the stages of an architectural project.

StageWhat is decidedResulting document
SurveyCondition and constraints of the propertyPlan of the existing space
Concept designLayout of the spaces, materials, 3D imagesChosen proposal
Detail designTechnical detail of the worksDrawings and bill of quantities
Tendering to building contractorsPrice of each taskBuilding contractors' proposals

Do I need a building permit or prior communication?

It depends on the type of works. Alterations inside a unit or building that do not modify the exterior are, as a rule, exempt from prior control (controlo prévio); if they affect the structure, they require a structural project (projeto de estabilidade) and a statement of responsibility (termo de responsabilidade). Works that alter the facade, the roof or the use may require prior communication (comunicação prévia) or a building permit (licença). Even for exempt works, the technical standards apply and, except for conservation works carried out only inside, the municipal council (Câmara Municipal) must be informed of the start of the works.

The classification is made at the start of the project, based on what you intend to alter, and determines the documents and the next steps. See the works exempt from prior control and prior communication.

How are proposals requested from building contractors?

Only with a specific design is it possible to request quotes that correspond exactly to what will be done. Without those documents, each company imagines different works.

Each building contractor receives the same drawings and the same bill of quantities. The proposals become comparable and misunderstandings during the works are avoided, because what was specified in the earlier stages is already accounted for.

A quote requested before the design is based on standard solutions, not on your design. If you then customise, the figures change. To go further, read how to budget for renovation works and how to compare renovation quotes. For a first order of magnitude, still without a design, use the renovation cost simulator. Also set aside a margin for unforeseen costs, especially in old buildings.

Who carries out the works?

The building contractor, hired directly by the Client on the basis of the proposals obtained from the design. spacelovers is an architecture studio and is not a building contractor. Decisions and contracts belong to the Client.

See how the selection of the building contractor works and what the building contract (contrato de empreitada) should include.

What logistics should be prepared before the works begin?

In an existing building, logistics decide whether the work flows or stops. Agree with the building contractor, before starting:

  • Access: whether the stairs, the lift and the doors allow materials, equipment and furniture through, and where the rubble goes out.
  • Neighbours and condominium: who informs them and when, which working and delivery hours are respected, and that nothing is left in the common parts without the condominium's agreement.
  • Site area: where materials and tools are kept, especially if you continue living in the house.
  • Services: which connections to the supply risers will be altered and when there may be water, electricity or gas cuts affecting the other owners.
  • Work schedule: the sequence of tasks, known to everyone involved.

Whatever is agreed should be included in the building contract.

What is technical assistance during construction like?

We provide technical assistance on the Client's behalf: construction follow-up, clarification of detailed questions and checking that the works follow the design. When an unforeseen situation arises, we help the Client decide. See technical assistance during construction and, for renovations, works management.

What mistakes should be avoided?

The most common are starting the works without a finalised design and requesting quotes based on vague ideas. See the most common renovation mistakes. If the renovation includes the kitchen, read how long a kitchen renovation can take.

Frequently asked questions

Do I need a design to renovate an apartment?

It depends on the works: some are exempt from prior control, others require prior communication or a building permit. Even when the law does not require it, a design helps define the works and obtain comparable proposals.

Who carries out the works?

The building contractor, hired directly by the Client. The studio produces the design and provides technical assistance during construction.

Can I request a quote before there is a design?

You can, but the figure is based on standard solutions and changes once the design is defined. For a first reference, use the simulator; for specific proposals, you need the design.

In which stage should I take part most?

In the concept design. That is where the layout of the spaces and the materials are decided, and those choices guide the whole project.

Can I keep living at home during the works?

It depends on the work. With light works it may be possible; with major works, involving dust, noise and water or electricity cuts, not always. Discuss the stages of the works with the building contractor before deciding.

Sofia SilvaFounder of spacelovers, an architecture and renovation studio in Lisbon.
Any questions? Talk to us.

Tell us what you need and we will outline the steps, permits and budget to expect.

Request a proposal +