In short
- The contract is entered into between the Client, as the owner, and the building contractor. spacelovers prepares the design and can carry out the technical review of the quotes, but is not a party.
- Above €20,000 (10% of the class 1 limit for construction licences), the building contract for private works must be in writing. For any works, it is prudent to have it in writing.
- The minimum legal content is: the parties, the contractor's licence or registration, the subject matter, the value and the completion period. It is advisable to add payments, guarantees, insurance and rules for changes.
- For buildings, the contractor is liable for defects for 5 years from handover, or for the agreed guarantee period.
- Changes and additional works (trabalhos a mais) are agreed in writing, with the price and time agreed before they are carried out.
- The legal review of the contract is a matter for a lawyer.
What is a building contract?
The Civil Code defines the building contract (empreitada) as the contract by which one of the parties undertakes, towards the other, to carry out certain works in return for a price (Article 1207).
In practice, it is the document that sets out what will be done, for how much, within what period and with what guarantees. The more complete the design and the bill of quantities (mapa de quantidades) that accompany it, the less room there is for doubt during the works.
Does the contract have to be in writing?
Yes, above a certain value. Building and subcontracting contracts for private works with a value above 10% of the class 1 limit for construction licences must be put in writing (Article 26 of Law No. 41/2015). With the class 1 limit set at €200,000 by Ministerial Order (Portaria) No. 212/2022, that threshold is €20,000.
The written contract must contain, as a minimum:
- the full identification of the parties;
- the identification of the contractor's construction licence, certificate or registration with the Institute of Public Markets, Real Estate and Construction (Instituto dos Mercados Públicos, do Imobiliário e da Construção, IMPIC);
- the subject matter of the contract, with the written and drawn documents, where they exist;
- the value of the contract;
- the completion period for the works.
Without the written form, the contract is void, but the contractor cannot invoke that nullity. Even below the threshold, our advice is the same: a written contract. Do not start the works without one.
Who are the parties and what is the subject matter of the contract?
The parties are the Client, as the owner, and the building contractor. The identification should be complete. For the contractor, it should include the number of the construction licence, certificate or registration issued by IMPIC, which entitles them to carry out construction activity.
spacelovers is not a building contractor, nor a party to the contract. The Client hires the building contractor directly. Decisions and contracts belong to the Client.
The subject matter of the contract describes the works and their location and lists the documents on which it is based: design, drawings, bill of quantities, specifications and detailed quote. What is in those documents is defined; what is not remains undefined.
Price and payments: what should be agreed?
State the value of the building contract and refer to the attached documents that support it, in particular the detailed quote and the bill of quantities. To compare quotes on an equal footing, see how to compare renovation quotes.
Also agree how and when payment is made. The most common forms are:
- *Measurement certificates (autos de medição):* payment follows the work carried out and measured.
- Staged payments: agreed amounts and moments, linked to the progress of the works.
Also set the method of payment, the reference to the applicable VAT and, where relevant, price revision, the security deposit (caução) and the consequences of late payment.
Can I pay everything in advance?
You should not. The Civil Code provides that, unless otherwise agreed or customary, the price is paid upon acceptance of the works (Article 1211). It is normal for the contractor to ask for an advance payment to start the work and buy materials, but paying in full before the works are done should be avoided.
Time limits and penalties
The contract should set the date by which the contractor undertakes to complete the work. The period may be extended, by agreement, to carry out additional works requested during construction.
It may also provide for penalties for failing to meet the deadline and, if the parties so agree, bonuses for meeting milestones. The amounts are set case by case, with legal support.
It is also advisable to define how communication will work during the works: the channel, who speaks to whom and how often. The owner and the contractor must cooperate so that the works proceed under the agreed conditions.
Guarantees, acceptance and insurance
Before signing, confirm the guarantee period, the method of acceptance of the works and the insurance.
Guarantee. For private works, the Civil Code applies. When the building contract concerns buildings or other immovable property intended to last a long time, the contractor is liable for defects and collapse for 5 years from handover, or for the agreed guarantee period (Article 1225). Defects must be reported to the contractor as soon as they are discovered: the time limits for reporting and for exercising your rights are short (Articles 1220, 1224 and 1225). Confirm the time limits for your case with a lawyer.
Acceptance of the works. Before accepting the works, the owner should inspect them (Article 1218). Acceptance in two stages may be agreed, with an initial inspection and a final inspection at the end of the guarantee period, and the retention of a security deposit, returned at the end.
Insurance. The contract should refer to the contractor's workers' compensation insurance (seguro de acidentes de trabalho), which is a requirement for their licence (Law No. 41/2015). Other insurance for the works may be agreed between the parties.
Changes to the works and additional works
During the works, decisions arise that were not foreseen: an exploratory opening reveals a new situation, the Client wants to change a finish. The contract should set out how additional works and omitted works (trabalhos a menos) are handled.
The golden rule is simple: no change goes ahead without written agreement on price and time. The contractor may not alter the agreed plan without the owner's authorisation (Article 1214 of the Civil Code), and the necessary changes must be communicated and authorised before they are carried out.
A complete quote, with demolitions, removals and finishing details included, greatly reduces additional works. See also the most common renovation mistakes.
Subcontracting
Decide whether you accept subcontractors and under what conditions. In a building contract for private works, subcontracting is only permitted to duly licensed companies, and the contractor may subcontract unless the contract provides otherwise (Article 20 of Law No. 41/2015). Before subcontracting, the contractor must check the subcontractor's licences with IMPIC.
The contract may therefore limit subcontracting or require prior authorisation for it.
What are the rights and duties of each party?
The Client (owner)
- Is entitled to works that comply with the contract, the design and the specifications.
- May inspect the progress of the works, at their own expense, provided this does not disrupt the normal course of the work (Article 1209 of the Civil Code), and should report defects as soon as they are discovered.
- May withdraw from the works, provided they compensate the contractor for expenses and work and for the profit the contractor could have made from them (Article 1229 of the Civil Code).
- Must pay the agreed price, cooperate in the works (respond to requests, provide information, obtain the authorisations that are their responsibility), inspect and accept the completed works and comply with the site safety and condominium obligations that apply to the case.
The building contractor
- Is entitled to receive payments in the agreed amounts and on the agreed dates.
- If the Client does not pay, has the remedies provided for in the contract and in the Civil Code, such as termination in the event of definitive non-performance. Before suspending work or terminating the contract, should seek legal advice.
- Must carry out the works in good faith and in accordance with good building practice, respect the design, supply materials in good time, keep workers' compensation insurance for staff and hand over the works on time.
Checklist before signing
- The parties and the contractor's licence or registration are identified and checked with IMPIC.
- The design, the bill of quantities and the detailed quote are attached.
- The price, the method of payment and the schedule are clear, with no full payment in advance.
- The completion period is set, with rules for extending it.
- The guarantee, the acceptance of the works and the insurance are defined.
- It is set out how changes and additional works are handled.
- Subcontracting and communication during the works are agreed.
- A lawyer has read the contract.
How does spacelovers help?
The contract is between the Client and the building contractor, and the legal review is a matter for a lawyer. We provide technical assistance on the Client's behalf: we prepare the design and the bill of quantities on which the quotes are based and carry out the technical review of the quotes received, so that they can be compared on an equal footing. During the works, we provide construction follow-up and check that the works follow the design.
See selecting a building contractor, technical assistance during construction and, in renovations, works management (gestão de obra). To prepare the quotes, read how to budget a renovation and the guide how a renovation project works.
Reference legislation
- Civil Code, Articles 1207 et seq. (building contract).
- Law No. 41/2015 of 3 June, as currently in force (regime governing construction activity), in particular Articles 20 and 26.
- Ministerial Order (Portaria) No. 212/2022 of 23 August (values of the construction licence classes).
This content is for information only and does not constitute legal advice. For your specific situation, legal advice should be provided by a qualified professional in the field.
Frequently asked questions
Do I need a written contract for small works?
The law requires the written form for building contracts for private works above €20,000. Below that amount, a written contract still protects both parties, because it records what was agreed.
Can I change the works after signing the contract?
Yes, in writing, with the price and time agreed before the change is carried out.
For how long is the contractor liable for defects?
For buildings and other immovable property intended to last a long time, for 5 years from handover, or for the agreed guarantee period (Article 1225 of the Civil Code). Report defects as soon as you discover them.
Can I withdraw from the works after they have started?
The owner may withdraw, but must compensate the contractor for expenses, work and the profit the contractor could have made from the works. Seek legal advice before deciding.
Is spacelovers a party to the building contract?
No. The contract is entered into between the Client and the building contractor. spacelovers is an architecture studio: it prepares the design, handles the licensing and provides technical assistance during construction.