In short
- Prior communication as the rule: when the planning parameters are defined in the plans, the works go ahead by prior communication, without an approval act by the municipal council.
- More responsibility: the municipal council's control becomes subsequent, and the developer, the author of the project and the site manager (diretor de obra) are answerable for compliance with the rules.
- Deadlines and tacit approval: decision deadlines have been revised and the municipal council's silence may count as approval (deferimento tácito).
- Planning title: its importance is reinforced, including in deeds for urban properties.
- Exempt works: they still exist, but now require a notification of the start of works.
This article is not legal advice. In complex cases, consult a specialist in planning law.
What is the RJUE and what did this decree-law change?
The RJUE is the Legal Framework for Urbanisation and Building, which defines how works are permitted and notified. Decree-Law No. 108/2026 was approved under Law No. 9-B/2026, of 6 March, and is the 21st amendment to Decree-Law No. 555/99, of 16 December.
It also amends the Legal Framework for Urban Rehabilitation (Regime Jurídico da Reabilitação Urbana, RJRU) and the General Regulation for Urban Buildings (Regulamento Geral das Edificações Urbanas, RGEU), and amends Decree-Law No. 10/2024, the Simplex Urbanístico. The new regime applies to processes started from 1 October 2026 and to those which, started earlier, were still at the stage of preliminary review and assessment (saneamento e apreciação liminar).
What changes in prior control?
Prior communication becomes the standard procedure
When the planning parameters are effectively defined in the planning instruments, the operation may go ahead by prior communication, without an approval act by the municipal council. Prior communication loses the preliminary review stage, so it must be properly documented from the outset.
In practice, the developer submits the documents, pays the fees and can start the works. The municipal council no longer approves in advance and inspects during and after the works.
The risk is clear: a project that does not comply with the rules may go ahead until inspection, a stop work order or fines. That is why the technical rigour of the architectural design is decisive.
More responsibility for those who develop and design
For works without a planning title or in breach of it, the law provides for joint and several civil liability of developers, building owners, building contractors, site managers, as the case may be (Article 100-A). Responsibility does not lie with the builder alone. Works without a title are subject to fines, which vary with the type of offence and the offender (Article 98).
In prior communication, the municipal council's subsequent control lapses within the period set by law, counted from payment of the fees or from the start of use, if later; inspection of the works remains possible at any time. The period for declaring permits null and void has been reduced (Article 69).
What happens to exempt works and prior communication?
Exempt works
Article 6 of the RJUE lists works exempt from a building permit (licença) and from prior communication. Among others: conservation works; interior alteration works that do not change heights, façades and roofs or affect structural stability; reconstruction works on buildings or units, without extension; and operations preceded by favourable prior information. Some energy efficiency improvements, such as solar panels or replacing window frames while keeping the exterior appearance, are works of minor planning significance (escassa relevância urbanística), also exempt, within the limits of the law.
Being exempt does not release the works from complying with the applicable rules. For exempt works, there is now a notification of the start of works to the municipal council, with the identification of the person responsible for carrying them out and the projects where applicable. The notification is made before the works begin, within the period provided for by law, with the exceptions set out in it (Article 80-A).
Find out more about works exempt from prior control.
Reconstruction and last valid precedent
A reconstruction that increases the volume or the area is no longer treated as a simple reconstruction, and is no longer exempt from prior control. For reconstructions that restore the situation of the last valid precedent (último antecedente válido), the exemption applies. The last valid precedent is the last valid and effective urban development operation, or the one that, at the time it was carried out, did not need a title.
Use of buildings
Buildings whose works were permitted, notified or exempt following positive prior information are subject to a prior communication for the purposes of use, with no mandatory inspection. In the other cases, a prior communication with a deadline is required: the property may be used once the legal period counted from submission has elapsed, and within that period the municipal council may reject the notification or order an inspection.
Prior information request
The prior information request (pedido de informação prévia, PIP) remains the way to confirm feasibility before the full design. When it covers all the applicable elements of Article 14(2), it exempts the works from a building permit and from prior communication, except for use or change of use (Article 6(1)(h)); for listed properties and protection zones, it allows the works to proceed by prior communication instead of a building permit (Article 4(4)(l)).
What are the changes to deadlines and tacit approval?
The municipal council's silence within the legal deadlines may count as approval. But works approved by silence may be in breach: tacit approval does not replace the technical check of the design.
Payment of fees by self-assessment has been extended, including cases of tacit approval. Proof of payment is no longer, on its own, a sufficient title: the planning title is formed by the proof of payment of the fees, the last application and the notification of approval or the proof of submission (Article 4-A).
In prior information requests and building permit applications, these changes stand out:
- the municipal council may extend deadlines for complex operations, on reasoned grounds.
In the prior information request, the law sets different decision deadlines depending on the type of request, counted from the end of the preliminary review. If there is no decision within the deadline, there is tacit approval, and favourable information has a period of validity.
The planning title and deeds
In transactions that transfer ownership of urban properties, the deed or contract must mention the planning title, the declaration that it exists or the declaration that it does not exist, failing which it may be annulled (Article 4-A(14)). If you are going to buy or sell, check this point early. See also Decree-Law 97/2026.
What has changed since the Simplex Urbanístico?
The Simplex Urbanístico, Decree-Law No. 10/2024, of 8 January, came into force, for the most part, on 4 March 2024 and was the step before this revision. Decree-Law No. 108/2026 amends it and incorporates several of its rules into the RJUE. Anyone with a process or a project planned under the 2024 regime should therefore confirm what remains in place.
A practical point: electronic processing of procedures becomes mandatory once the platform is made available, and the decree-law does not set a date for this. Check with your municipal council how to submit the application.
What stays the same?
- The obligation to comply with the applicable regulations, even for exempt works.
- The architectural design and the engineering specialty projects, with the authors' statements of responsibility (termos de responsabilidade).
- The importance of the municipal master plan (Plano Diretor Municipal, PDM): without defined parameters, prior communication may not be possible and prior information remains the safest route.
- The municipal council's role in inspection, now more concentrated during and after the works.
What should you do now if you have a process under way?
- Review the process in light of the new regime. Some building permit applications may move to prior communication. If your process was still at the preliminary review and assessment stage on 1 October 2026, you can adapt it to the new regime.
- Confirm that the PDM defines the planning parameters for your plot before opting for prior communication.
- Make sure the application is complete. Responsibility for compliance lies with the applicant.
- Consult a specialist in complex cases, such as rehabilitation in an Urban Rehabilitation Area (Área de Reabilitação Urbana, ARU), reconstruction with a change in volume or transactions involving properties without a planning title.
- Update draft deeds, including the declaration on the planning title.
Frequently asked questions
If the municipal council does not reply, can I start the works on the basis of silence?
It depends on the procedure and the applicable deadlines. In general, silence may count as approval, but the design must comply with the rules. In the case of tacit approval, the title is formed by the proof of payment of the fees, the application and the proof of submission.
Does the new regime change what I pay in fees?
Payment by self-assessment has been extended. The amounts and rules depend on each municipality's regulations.
Is an architect still needed?
Projects must be signed by qualified technicians and technical responsibility has been reinforced. Only technicians who are legally qualified and registered with the respective professional body may sign projects.