Architecture · Procedure

Pre-application enquiry (PIP).

Updated on 17 November 2026 · Legislation as currently in force

Find out what you can build before you spend on the design.

Perspective of the proposed mansard roof with dormer windows above the parapet façade, Bairro Alto
On this page
  1. 01What it is
  2. 0214(1) and 14(2)
  3. 03Elements of the PIP
  4. 04Deadlines
  5. 05Extensions
  6. 06Rules in force
  7. 07Changes to the request
  8. 08Complete PIP
  9. 09After the PIP
  10. 10Validity and renewal
  11. 11Differences
  12. 12Advantages
  13. 13Who can apply
  14. 14If the design changes
  15. 15When it makes sense
  16. 16What we do
  17. 17Documents
  18. 18Documents by operation
  19. 19Procedure
  20. 20Frequently asked questions
  21. 21Sources
Book a meeting +

In 30 seconds

  • The PIP asks the municipality (Câmara Municipal), before the design, whether an urban development operation is viable and subject to which constraints (Article 14 of the RJUE, the Legal Regime for Urbanisation and Building).
  • There are two types: the Article 14(1) enquiry, which is simpler, and the Article 14(2) enquiry, with more elements and stronger effects.
  • With an Article 14(2) PIP, when it is favourable and covers all the applicable elements, the works may be exempt from a building permit and from prior communication (comunicação prévia), except for use or change of use (Articles 6(1)(h) and 17(2)).
  • Estimated total period, without external consultations: around 45 days (14(1)) and 60 days (14(2)), from 1 October 2026.

The PIP is a formal consultation. The municipality states what the site allows (uses, massing, building heights (cérceas), land cessions (cedências)) before you invest in the specialist engineering designs. It is a way of reducing the risk of a design that later proves unviable.

The PIP is informative in nature: it is for finding out, not for obtaining a licence. The municipality's reply must be read together with what was asked.

Article 14 of the RJUE

Article 14(1) PIP and Article 14(2) PIP

Aspect Article 14(1) PIP Article 14(2) PIP
Purpose Viability of the operation and its constraints. Viability with more complete elements. Applies to all urban development operations, including building works within a subdivision (loteamento).
Assessment 15 days. 30 days (45 days for subdivision operations).
Estimated total period, without consultations 45 days. 60 days.
Can it make the works exempt? No. Yes, when favourable and if it covers all the applicable elements (Articles 6(1)(h) and 17(2)).
Documents required Ordinance (Portaria) no. 320/2026/1. Ordinance (Portaria) no. 320/2026/1.

Article 14(2) of the RJUE

What must a PIP for building works show?

A PIP for building works shows the municipality, in the necessary detail, what is intended and where: siting, massing, uses, infrastructure and charges. The more complete it is, the firmer the reply and the less contention there is in the following application.

Element What is shown Where it is checked
Massing, alignment, building height and siting How the building, and any boundary walls, fit into the site Municipal master plan (PDM), detailed plans and regulations
Architectural design and descriptive report The intended solution, with the schedule of uses Drawings and written documents of the request
Schedule of uses Areas by use, number of dwellings and other units, ancillary and technical areas Municipal regulations and plan parameters
Local infrastructure The connection to the general infrastructure networks Municipal services and utility operators
Estimate of development charges Fees and compensation that may be due Municipal fees regulations
Areas to be ceded Green spaces, community facilities and road infrastructure Plan and municipal regulations

To see how an operation is prepared before the request, read about architecture projects and technical due diligence.

Articles 11 and 16 of the RJUE

How long does it take?

Legal estimate without consultations with external bodies. Consultations and extensions lengthen the process.

20 days

Preliminary review (saneamento): the municipality checks that the request is properly documented.

10 days

Correction (aperfeiçoamento): the period to correct or complete the request.

15 or 30 days

Assessment and decision: 15 days for 14(1); 30 days for 14(2), which may be extended once, with justification.

Article 16(7) of the RJUE

Can the deadlines be extended?

Only for an Article 14(2) PIP. The municipality may, exceptionally, extend the decision period once only, by the same length: 30 days become 60 and, for subdivision operations, 45 days become 90. The ground is the particular complexity of the operation, namely subdivisions with urbanisation works or operations with a significant impact or an impact similar to a subdivision. The decision lies with the mayor (presidente da Câmara) and must be notified to the applicant by the end of the preliminary review period. There is no extension for an Article 14(1) PIP.

Decree-Law no. 108/2026 (Decree-Law)

Rules in force since 1 October 2026

Deadlines

Preliminary review of 20 days, correction of 10 days and a decision within 15 days (14(1)) or 30 days (14(2); 45 days for subdivision operations), without external consultations.

Tacit approval

If the municipality does not decide within the deadline, the request is deemed tacitly approved (deferimento tácito) (Article 16(6)).

Article 16(5) of the RJUE

What if the PIP is unfavourable or the request has to change?

If the information is unfavourable, the municipality must state the terms on which the operation, if viable, can be revised in a subsequent procedure so as to comply with the applicable planning rules, namely those of the municipal or intermunicipal land-use plan or of the subdivision operation. After an unfavourable decision, the operation is therefore revised in a following procedure.

Before the decision, the municipality may notify the applicant to correct or complete the request within 10 days (Article 11).

Articles 6 and 17 of the RJUE

Does a complete PIP remove the need for a licence?

It does so only if it is an Article 14(2) PIP that is favourable, complete and carried out exactly on the terms assessed. When it covers all the applicable items, the works may start without a licence or prior communication, but the municipality must still be told when the works start and, at the end, the use must be communicated (article 6(1)(h) and article 17(2)). For listed buildings, buildings in the process of being listed, or buildings within a listed group or site, and, in a protection zone, for works the law subjects to a licence, a favourable Article 14(2) PIP does not grant exemption: it leads to the prior communication regime (article 4(4)(l)).

To exempt the works and avoid further consultations, the Article 14(2) request must contain all the items applicable to the operation. If any applicable item is missing, the exemption does not apply: a licence or prior communication follows, as the case may be. Carrying out works that do not comply with the conditions of the pre-application opinion may lead to penalties (article 98).

Article 80-A of the RJUE

After a favourable Article 14(2) PIP

When the works are exempt following the PIP, the notice of the start of works must be accompanied by more documents (Article 80-A(4)):

  1. Specialist engineering designsWith the statements of responsibility (termos de responsabilidade) of their authors.
  2. Coordinator’s statement of responsibilityFrom the design coordinator.
  3. Fees and chargesProof of payment of the fees and other charges due.
  4. Land cessionsProof that the cessions have been made, where applicable.

The notice is displayed on site, visible from the public road, up to five working days before the works begin (paragraph 5), and the information lapses if the works do not begin within one year (paragraph 6).

Article 17(5) to (7) of the RJUE

How long is a favourable PIP valid?

Two years, counted from the notification of the favourable decision or from the formation of tacit approval. Within that period, for an Article 14(1) PIP, the building permit application or the prior communication must be submitted; for an Article 14(2) PIP, the urban development operation must be started.

Once the two years have ended, the applicant may ask the mayor, once only, for a declaration that the factual and legal grounds of the favourable decision still apply. The mayor decides within 20 days. If the mayor declares that they still apply, or does not reply within the deadline, the applicant has a further year to submit the building permit application or the prior communication or, for an Article 14(2) PIP that contains all the applicable elements, to start the operation.

Articles 4, 14 and 17 of the RJUE

How does a PIP differ from a building permit and from prior communication?

The PIP asks the municipality whether an operation is viable and on what conditions. It does not grant a title to carry out works. The building permit and prior communication are the procedures that allow the works to be carried out.

PIP Building permit Prior communication
Purpose Find out whether it is viable and with what constraints Obtain a licence before the works Notify the works and carry them out once the fees are paid and the start has been reported
Does it grant a title for the works? No (except a favourable Article 14(2) PIP, when the works become exempt) Yes There is no prior act by the municipality
Specialist engineering designs As a rule, not required at this stage Submitted with the application or after the architecture Submitted together with the architecture
Effect on the following application Binds the municipality if the grounds still apply — —

See the pages on the building permit and prior communication.

Articles 15 and 17 of the RJUE

What are the advantages of a PIP?

  • Information: it sets out the constraints that apply to the site, such as infrastructure, easements, public-interest restrictions, planning indices, building heights and setbacks. It is useful before buying a plot or a property, to understand what can be done. It is not a valuation.
  • Guarantee: the favourable information binds the municipality in the following applications, while it is valid and as long as the intentions presented are maintained (see “How long is a favourable PIP valid?”).
  • Simplification: external bodies that have already given their opinion in the PIP do not have to be consulted again, if the design respects the grounds of the PIP. If the terms change, a new consultation may be needed.

Article 14 of the RJUE

Who can request a PIP and how is it submitted?

Anyone with an interest can request a PIP, even without being the owner. The request is made to the municipality where the site is located, with the form and the elements that the municipality requires.

  • If the applicant is not the owner, the request identifies the owner and the holders of other rights in rem, with the land registry certificate, because the municipality has to notify them of the procedure.
  • The request states the intended operation and the matters on which an opinion is sought.
  • The procedure is subject to fees under the municipal regulations; the amount depends on the municipality.

We can prepare the request and follow it through: request a proposal.

Article 17 of the RJUE

What happens if the design changes after a favourable PIP?

The favourable information binds the municipality as long as the design respects the intentions presented in the PIP. If the underlying conditions change, such as massing, use or siting, the following application may not be accepted and the external bodies may have to be consulted again. Before changing the design, it is advisable to confirm the effect of the change with the architect.

Please note

When it makes sense to request a PIP

  • Before buying a plot or a property with extension potential
  • When there are doubts about building height, massing or planning indices
  • When the property is in a protection zone or is subject to constraints
  • When a change of use is intended
  • In rehabilitation projects with heritage restrictions
  • In subdivisions and operations of similar impact

If the works are simple and the planning framework is clear, it may not be worthwhile. We will tell you so at the first meeting.

The studio's role

From the site to the opinion

Full renovation New plasterwork, windows, building services

Constraints and plans

Site analysis
House renovation in Alcochete. Outdoor landscaping area designed in an integrated way, with a swimming pool and a covered part for meals and contemplation.

What the site allows

Viability
Project image of the house in Alcabideche: car access to the basement next to the wall and the garden

Descriptive report and drawings

Request
Rehabilitation of a building in Campo de Ourique, Lisbon: windows with Juliet balconies

From the opinion to the design

Design

Ordinance (Portaria) no. 320/2026/1

What the request includes

  1. Application form and standingCode of the permanent land registry certificate and, if necessary, documents proving the applicant’s right.
  2. Location and plansLocation plan and extracts from the plans of the applicable territorial plans.
  3. Topographic surveyWhere required.
  4. Descriptive reportDescribes the operation, the schedule of uses and the area, and shows compliance with the applicable rules.
  5. DrawingsDepending on the type of PIP and the operation.
  6. Statement of responsibilityFrom the author, with professional qualification and civil liability insurance.
  7. External opinionsOr proof of the consultation, if they are not issued within the deadline (Article 15 of the RJUE).

Ordinance (Portaria) no. 320/2026/1

Which documents vary according to the operation?

Operation Documents usually requested
Building works Architectural design at the required scale, local infrastructure, land cessions, photographs of the property (for alterations, reconstructions and extensions), estimate of charges, accessibility plan, acoustic study and statements of responsibility
Demolition Description of the state of repair, drawings showing the demolition techniques and the retaining structures, photographs and statements of responsibility
Change of use Plan of the building or unit, demonstration that the use is admissible and that the space is suitable, and statement of responsibility
Subdivision and urbanisation works Larger-scale drawings and specific studies; we analyse each case individually

The exact list depends on the type of PIP, the municipality and the ministerial order in force.

Frequently asked questions

Frequently asked questions

Legal sources

Sources

  • RJUE (Decree-Law no. 555/99, as currently in force), Articles 6, 14 to 17 and 80-A
  • Decree-Law no. 108/2026, of 29 May
  • Decree-Law no. 155-B/2026, of 31 July (in force from 1 October 2026)
  • Ordinance (Portaria) no. 320/2026/1, of 31 July

Last legal review: November 2026. Legislation consulted on 10 November 2026, as currently in force.

This page is for information only; it does not replace the analysis of each case, nor does it constitute legal advice. How a particular project is framed depends on the property, its location, the territorial management instruments and the applicable municipal regulations.

How we work

We think before we build

Discover the process +
1. First contact

Online meeting and questionnaire.

2. Proposal

Sent by email, with the scope and the fees by stage.

3. Concept design and design

Delivered by email and presented at a meeting.

4. Building permit

Handled entirely by us.

5. Works

Fortnightly or weekly follow-up, with reports.

6. Handover

Final visit with the Client.

Client testimonials

What our Clients say.

Google reviews

Client reviews on Google

Sandra Castanho
Sandra CastanhoMay 2019 · Google review
★★★★★

Atendimento de excelência e grande profissionalismo. Recomendo vivamente!

Medical institute renovation, Lisbon
jose martins
jose martins2019 · Google review
★★★★★

Remodelação de excelência.

Beatriz Guedes
Beatriz GuedesJune 2023 · Google review
★★★★★

Nesta aventura da renovação da nossa primeira casa, pedimos à equipa SpaceLovers para nos ajudar no “bicho de sete cabeças” que eram as escadas. É de destacar não só o profissionalismo e rapidez na realização do projeto, como também a disponibilidade para nos esclarecer todas as dúvidas (iniciais e ao longo do processo). Agradecemos ao Rui e à Sofia por nos terem ajudado a tornar realidade as ideias que tínhamos para a nossa casa.
Caso pretendam renovar a vossa casa, contactem, definitivamente, a equipa SpaceLovers!

House renovation, Ericeira
Miriam Araújo
Miriam AraújoOctober 2019 · Google review
★★★★★

Um projecto de excelência, com bom gosto, simplicidade e atenção super detalhada às necessidades e gostos do Cliente. Resposta super rápida e serviço super bem organizado. Estamos muito contentes com a nossa escolha!

Apartment renovation, Lisbon
Ferdinand Jaggi
Ferdinand JaggiApril 2026 · Google review
★★★★★

Servicio muito rapido e super competente! Muito agradecido num caso difficil à solver!
Fernando

House renovation, Lagos
Sónia Caldeira
Sónia CaldeiraJanuary 2020 · Google review
★★★★★

Profissionalismo, coerência, capacidade de resposta às necessidades do Cliente, flexibilidade, pontualidade, disponibilidade, bom gosto… muito satisfeita com o trabalho da Spacelovers. Não hesitarei em contratar novamente os seus serviços e em recomendá-los a quem precisar de um projecto de Arquitectura.

Building rehabilitation, Lisbon
Bruno Cadilhe
Bruno CadilheApril 2025 · Google review
★★★★★

Eles têm a experiência necessária para oferecer um serviço excelente e profissional de alto nível.

Apartment renovation, Tomar
David Hagmann
David HagmannMay 2022 · Google review
★★★★★

Sofia and Rui are simply amazing. They are very professional, always respond to your questions, and really care about customer satisfaction. They are very proactive if any doubts arise and explain thoroughly which possible options you have. I would definitely work with them again in my next renovation project and can recommend them without any doubts.

Apartment renovation, Lisbon
Cristina Repas
Cristina Repas2022 · Google review
★★★★★

Profissionalismo, simpatia, e atenção ao detalhe.
Muito obrigada Sofia!

Marco Magalhães
Marco MagalhãesMay 2020 · Google review
★★★★★

Estou mais que satisfeito com o Excelente trabalho e Orientação prestada pela Sofia e Rui neste projecto de Arquitectura para a construção da nossa moradia. Muito abertura e capacidade de interiorizar os nossos desejos.
Sempre prestáveis e simpáticos. Todas as etapas concretizadas dentro dos prazos estipulados.
Muito obrigado à Sofia e ao Rui

Single-family house, Sintra
José Pedro Fazenda Martins
José Pedro Fazenda MartinsMay 2024 · Google review
★★★★★

Desde o primeiro contacto estabelecido, achámos toda a equipa muito profissional, em especial o arquitecto Rui que trabalhou de forma mais próxima connosco. Tiveram uma grande atenção aos detalhes, não perdendo de vista o nosso objectivo com a obra de recuperação e os prazos foram sempre cumpridos; muito satisfeitos com a qualidade do projeto, do acompanhamento da sua execução e do resultado final.

Apartment renovation, Lisbon
Ricardo Veiga Carvalho
Ricardo Veiga Carvalho2018 · Google review
★★★★★

Fantástico atendimento, com resposta muito rápida e com grande qualidade. Recomendo vivamente..

A selection of published reviews, shown as in the original. See all reviews on Google (4.8 · 47 reviews) ↗

Request a proposal

Do you have building works in mind? Let's talk about your project.

Request a proposal +4.8 ★ · 47 Google reviews