In short
- Without a design there are no comparable quotes: ask for quotes based on the same design and the same list of works.
- Look for experience in works of the same type, not just the best-known company.
- Ask who your contact person is, what is subcontracted and what is left out of the quote.
- Check the company's licences with the Institute of Public Markets, Real Estate and Construction (Instituto dos Mercados Públicos, do Imobiliário e da Construção, IMPIC) and ask for proof of workers' compensation insurance (seguro de acidentes de trabalho).
- The studio prepares the design and supports the decision; whoever carries out the works is chosen and hired by the Client.
Who does what in an interior renovation?
A renovation involves several roles, which are worth distinguishing.
- The Client decides, pays and hires.
- The architecture studio designs, coordinates the information and provides technical assistance within the scope agreed with the Client.
- The building contractor carries out the works, with their own team and, often, specialist subcontractors (flooring, kitchens, tiling, electrical work, among others).
spacelovers is not a building contractor: the Client hires whoever carries out the works directly.
Who comes in at each stage?
A renovation is multidisciplinary: no single professional does everything, and the coordination between them all matters as much as the competence of each one. The usual order is as follows.
- The Client defines needs, priorities and investment.
- The architect and/or the interior designer carry out the survey, the study and the design. The architect looks at the building and the legal framework; the interior designer at how the space is lived in and at the interior detail (layout, materials, lighting, joinery). In many renovations they are the same team.
- The engineering specialty designers come in when the intervention involves the structure, electrical installations, water and drainage, gas or HVAC. Not every renovation requires every specialty: see engineering specialty projects (projetos de especialidades).
- The building contractor and the trades price, contract and carry out the work once the design is defined. The most common trades are bricklayer, plumber, electrician, plasterboard installer, air-conditioning installer, tiler and marble mason, carpenter or joiner, metalworker and glazier, plasterer and painter.
- The suppliers deliver materials and equipment in coordination with the building contractor. Decide early who orders each material, so that the works do not stop waiting for a part.
- The decorator puts the finishing touches to the space at the end, with loose furniture, textiles and accents.
If the works require scaffolding or skips on the public road, confirm with the building contractor, before starting, who applies to the municipality for authorisation.
How do you gather candidates?
Start with recommendations from people who have had similar works done. Complement them with online research and visit the companies' websites.
Look for completed works of the same type, a clear description of what they do and the way they talk about the process. If you have a design, ask the studio whether it can tell you what to require from whoever carries out the works. The studio can support the market consultation; see the building contractor selection stage.
To get an order of magnitude before contacting companies, you can use the renovation cost simulator. It gives reference values, not a proposal.
What questions should you ask each candidate?
- Have you carried out works of this type and size? Ask for examples you can visit or see.
- Who will be my contact person from start to finish?
- What is done by your own team and what is subcontracted? It is normal to have specialists for each type of work; it is worth knowing who they are.
- What licences and insurance does the company hold? Ask for the number of the construction licence (alvará) or IMPIC registration and check it on the IMPIC website. Also ask for proof of current workers' compensation insurance.
- Do you plan the works? Works with a defined sequence have fewer surprises.
- What is included and what is not included in the quote? Ask for the list of items.
- Do you visit the property before pricing? Pricing without seeing the site usually produces inaccurate quotes.
What should you ask for and check with each company?
Licences
Before comparing prices, compare documents. Ask for the construction licence (alvará de construção civil) or, for smaller private works, the contractor's certificate (certificado de empreiteiro) (Law No. 41/2015). The licence defines, by category, the work the company may carry out and, for private works, is granted by class: confirm that it covers your works. Workers' compensation insurance is one of the requirements for obtaining these permits, so also ask for proof, with its validity. Check that the company's details match across all documents.
Technical capacity and site lead
The company should have, on its staff or through partners, professionals capable of delivering the design. Unexpected decisions come up on site, such as a wall hiding a surprise or a service that is not where it should be: ask who resolves them and with what experience. Also ask who is in charge of the site day to day, how to contact them and how they liaise with the designer. This person in charge should not be confused with the site manager (diretor de obra), a role provided for by law for works subject to prior control (controlo prévio). If the decision involves the design, the communication should also go through the architect who authored it.
Subcontracting
It is normal to subcontract trades such as carpentry, electrical work or plumbing. The law allows subcontracting to licensed companies, unless the contract provides otherwise, so state in the contract whether you authorise it. Your contract is with the main contractor; the subcontractor is bound to the main contractor, and it is advisable to set out in writing who is responsible for the guarantee. For more demanding work, ask for photographs of, or visits to, the subcontractor's previous work: for carpentry, for example, see furniture already installed.
Communication during the works
Agree from the outset who will talk to you and by what means, how changes are recorded and approved, and how neighbours are notified of noisy work or of service interruptions. See logistics in renovation works.
Guarantee and after-works support
The guarantee should be set out in the building contract (contrato de empreitada). What counts, however, is the company's real response: talk to previous Clients and ask how defects and complaints were handled. The law provides a specific regime for the contractor's liability for construction defects in buildings (Civil Code, Article 1225); check in the contract how it applies to your case.
Site safety
Look for a company that provides personal protective equipment to all workers and visitors (helmet, safety footwear, high-visibility vest and, depending on the stage, gloves and goggles) and ask how it organises safety on site.
How do you compare the quotes?
Compare quotes that start from the same design and the same bill of quantities (mapa de quantidades). If each company interprets the work in its own way, the prices are not comparable.
Check in each quote:
- items included and items excluded;
- materials and brands specified, or the room for choice left to the contractor;
- work with price to be defined;
- payment terms;
- work programme.
The full method is in how to compare renovation quotes.
What warning signs should weigh on the decision?
- A verbal-only quote or one without a list of works.
- A quote prepared without seeing the property or the design.
- A price very different from the other quotes, without explanation.
- Vague answers about subcontracting, insurance or licences.
- Pressure to decide quickly.
- Reluctance to put everything in writing.
And the contract?
Before starting, agree in writing the scope, the price, the payment terms and the work programme. See the article on the building contract. Above a certain value (10% of the class 1 limit for construction licences, set by ministerial order (portaria)), the law requires a written contract, which must identify the parties, the company's licences or IMPIC registrations, the works (with the written and drawn documents), the price and the completion period. Even below that value, it is advisable to have everything in writing.
What does the studio do before and during the works?
spacelovers prepares the design and the bill of quantities, supports the Client in the market consultation and in reading the quotes and provides technical assistance during construction within the scope agreed with the Client. Find out more about technical assistance during construction and the stages of an interior renovation project.
The decision on who carries out the works always belongs to the Client.
Frequently asked questions
Can I ask for quotes before having a design?
You can, but you will only get a generic estimate. For comparable and realistic quotes, the design and the list of works must exist first.
What do I do if the quotes are very different?
Ask the companies to justify the differences item by item. Often the explanation is a different scope, different materials or omitted items.
Do I need an architect and an interior designer?
Not always. For an interior-only intervention, one of the two may be enough. If the works involve walls, installations or licensing, an architect is, as a rule, necessary.
Does the studio continue to be involved once I have chosen the company?
The studio remains responsible for the design and can help with the technical reading of the proposal and the quote. The execution of the works rests with the company the Client has hired.
This content is for information only and does not constitute legal advice. For your specific situation, legal advice should be provided by a qualified professional in the field.
Photo: solimonster (Unsplash).