In short
- A space is only legally a home once the change of use process has been formalised, whether for your own home or for letting.
- DL 10/2024 no longer requires approval from the condominium owners' meeting (assembleia de condóminos) for a change of use in horizontal property (propriedade horizontal), but works on the common parts still need authorisation.
- The municipal council may require architectural and engineering specialty projects, depending on whether or not the works are subject to prior control.
- Feasibility depends on the municipal master plan (Plano Diretor Municipal, PDM), the municipal regulations and the technical conditions: areas, ceiling height, natural light, structure, acoustics, energy efficiency and accessibility.
- After the conversion, the deed establishing the horizontal property (título constitutivo da propriedade horizontal) must be updated.
- Costs and timescales vary with the property and the works required.
Why convert a shop into a home?
Converting unused shops, warehouses and offices makes it possible to reuse the existing building and the infrastructure already in place, such as water, drainage, electricity and structure. It is therefore a coherent option from a sustainability point of view. What remains to be seen is whether the property has the capacity to be transformed and to provide the required habitability conditions.
A former shop can become an apartment and an office can become a loft. But these spaces were designed for commercial use: they often lack the privacy a home requires and mean altering façades. This is one of the main challenges, because it may require the authorisation of the condominium owners.
There are already many commercial spaces where people live without meeting all the requirements. For a property to be legally used as a home, whether your own or for letting, the change of use process must be formalised.
What changed with Decree-Law 10/2024?
One of the main provisions of the Simplex urbanístico simplifies conversion in buildings under horizontal property. Approval from the condominium owners' meeting, which previously required unanimity, is no longer needed to change the use. This reduces red tape and, in part, costs.
There are, however, two caveats:
- if the conversion requires altering the architectural line or the aesthetic arrangement of the building, approval by a two-thirds majority of the total value of the building is required (Article 1422(3) of the Civil Code);
- if, to comply with the legislation, works are needed on the common parts, such as façades or structure, the authorisation of the condominium owners is required, because those parts are being altered.
Do I need to change the deed establishing the horizontal property?
Yes. Once the conversion from shop to home is complete, the change to the deed establishing the horizontal property must be formalised and the residential use associated with the unit (fração), by public deed or authenticated private document. The condominium administrator must also be notified, within 10 days, under Article 1422-B of the Civil Code.
Only then is the property legally used as a home. This change is made unilaterally by the owner of the unit.
What procedure does the municipal council require?
Existing non-compliance cannot be made worse, let alone new non-compliance created. That is why the technical and legal analysis must come before any decision.
Where there were no works, or only works exempt from prior control, use is authorised through prior communication (comunicação prévia) with a deadline, to demonstrate that the building or unit is suitable for the intended purpose. The application includes documents that vary with the procedure: proof of standing, extracts from the zoning plans, location plan, descriptive and justification report (memória descritiva e justificativa), among others.
With the changes made by DL 10/2024, it is important to understand which situation your intervention falls into:
What if the intervention is subject to prior control?
Article 62-A of the Legal Framework for Urbanisation and Building (Regime Jurídico da Urbanização e da Edificação, RJUE) applies. After works that have been permitted, notified or exempted through favourable prior information, use is authorised through prior communication, and the building or unit may be used immediately after submission, with subsequent control by the municipal council.
What if there was no previous urban development operation?
Article 62-B of the RJUE applies. A change in the use of a building or unit that is not preceded by an operation subject to prior control is the subject of prior communication with a deadline. The property may be used 10 days after submission; within that period, the municipal council may reject the notification or order an inspection. It serves to demonstrate and declare that the use is admissible under the rules that set the permitted uses, and that the building or unit is suitable for the intended purpose, and it may provide for mixed uses.
What if the works are exempt from prior control?
After works exempt from prior control, use follows the prior communication with a deadline described above. On these works, see the article on exempt works.
The architectural and engineering specialty projects are generally submitted to the municipal council or to other bodies when the intervention involves prior control.
What should you check before converting?
Zoning and local regulations
Consult the municipal master plan to find out whether the location excludes residential use. Also consult the municipal urbanisation and building regulations of the municipality where the property is located (in Lisbon, the Regulamento Municipal de Urbanização e Edificação de Lisboa, RMUEL), which may set requirements for new dwellings, such as compatibility of uses, a place for drying laundry and parking.
Habitability conditions
Study whether the existing conditions comply with the applicable legislation, including the General Regulation for Urban Buildings (Regulamento Geral das Edificações Urbanas, RGEU): minimum areas, ceiling height, natural lighting and ventilation. It is important to know what already exists and what can be introduced through works.
Structure and safety
Assess whether the structure is suitable for residential use. If there is structural alteration or damage, check whether a seismic vulnerability assessment study is required. Also check emergency exits, fire detection and access for people with reduced mobility.
Natural light and ventilation
Habitable rooms must make the most of natural light and have adequate ventilation.
Acoustic insulation
Noise from neighbouring or outdoor areas must be reduced. An analysis and an acoustic design project will be required.
Energy efficiency
Plan for thermal insulation, window frames with double glazing and thermal break, and efficient heating and cooling systems, in line with nZEB buildings.
Interior layout
A home must provide certain spaces, with minimum dimensions and areas. Converting a shop does not exempt you from these requirements.
Accessibility
Ensure accessible routes and facilities, with ramps, lifts and suitable bathrooms, in accordance with Decree-Law No. 163/2006, of 8 August. See the accessibility plan.
How do you know whether the space can be converted?
The starting point is a change of use feasibility study, carried out by an architecture studio. For this, you need to gather:
- the certificate from the Land Registry (Conservatória do Registo Predial);
- the property tax record (caderneta predial);
- the works file held by the municipal council;
- the existing occupancy licence (licença de utilização);
- a visit to the property to assess the built conditions (see on-site survey).
Adaptations to the building's original design and structural and infrastructure works may be needed to meet the habitability standards. This involves additional planning and investment.
How much does it cost to convert?
The costs include design and works and vary with the size of the property, the complexity of the works and the materials. They should be part of the feasibility analysis, especially if you have not yet bought the property and it has a commercial or services use. For figures tailored to your property, request a proposal. If, instead of converting, you are considering building from scratch, see the guide to building a house.
Frequently asked questions
Can I let a shop I converted without formalising the change of use?
For the property to be legally used as a home, whether as your own home or for letting, the change of use process must be formalised.
Does a change of use need an architectural design?
It depends on how the intervention is classified (with or without prior control) and on what the municipal council requires. Generally, when there is prior control, architectural and engineering specialty projects are submitted. A feasibility study helps you understand your case.
Do the condominium owners have to approve the conversion?
A change of use to residential no longer needs the authorisation of the other condominium owners: it is enough to notify the administrator within 10 days (Article 1422-B of the Civil Code). Works on the common parts, such as façades and structure, still require authorisation; those that alter the architectural line or the aesthetic arrangement require two thirds of the total value of the building.