In short
- It is a technical report prepared by structural engineers, which assesses the seismic resistance of the building and identifies improvements.
- It is required when there is evident deterioration, a change in structural behaviour, a cost of intervention above 25% of the equivalent new construction cost, or an intervention area above 25% of the gross floor area.
- It is submitted together with the architectural design, not after approval.
- It also applies to works exempt from prior control, in cases of higher cost or evident deterioration.
- If the building does not meet the requirements, a seismic or structural strengthening project is needed.
What is the seismic vulnerability assessment study?
It is a technical document that assesses the risk of damage to a building during an earthquake. It analyses the resistance of the structure, materials and foundations, identifies vulnerable areas and recommends measures to improve resistance. It also shows the impact of the alterations that are intended.
It is prepared by engineers specialising in structures, with specific knowledge of seismic analysis.
When is it mandatory?
It is mandatory in extension, alteration or reconstruction works, to determine the building's capacity to resist seismic action, whenever one of these conditions, set out in Ministerial Order No. 302/2019 of 12 September, is met:
- evident signs of deterioration of the building's structure;
- interventions that alter the structural behaviour of the building;
- construction cost of the intervention, in its entirety (even if the works are interior), above 25% of the equivalent new construction cost;
- intervention area, including demolitions and extensions, above 25% of the building's gross floor area.
In buildings of importance class III (for example, schools) or IV (for example, hospitals, fire stations, power stations), the report is also mandatory, with the thresholds reduced to 15%.
When is the study submitted?
It is submitted at the stage when the architectural design is assessed, whether in a prior information request (pedido de informação prévia), a building permit application (licenciamento) or a prior communication (comunicação prévia).
Unlike the other engineering specialties, it does not wait for approval of the architecture: it is submitted together with the design, to confirm the structural feasibility of the intended operation. This way, the owner knows early on whether the intervention will require something more extensive.
What about works exempt from prior control?
The report is also needed for works exempt from prior control when the alteration involves a cost above 25% of the equivalent new construction cost or when there is evident damage from deterioration of the structure. The other two conditions apply to works subject to prior control.
What does the report contain?
In Lisbon, ReSist, a team of Lisbon City Council (Câmara Municipal de Lisboa), has published a document that sets out the structure of the report; in other municipalities, check whether there is specific guidance. In general terms, it has three parts:
- Characterisation, inspection and diagnosis of the existing construction: gathering of the available information, geometry of the structure, characterisation of the materials and structural elements, defects and type of ground.
- Structural safety assessment: assessment of seismic vulnerability according to standard NP EN 1998-3 or, where applicable, by simplified analysis methods.
- Conclusions.
In addition, the report describes the site (location, soils, geological hazards), the building and the elements under study, the vulnerability analysis, the recommendations for improvement and the appendices (drawings, calculations, tables).
It is common to include on-site intrusive investigations (sondagens), which make it possible to check the type and quality of the materials and to detect defects.
When is a seismic strengthening project needed?
When the report concludes that the building does not meet the safety requirements for 90% of the seismic action defined in the assessment and rehabilitation standard. In that case, it is mandatory to prepare the seismic or structural strengthening project.
The study is therefore a key part of the structural stability project and carries weight in coordination with the other engineering specialty projects.
What is it for, in practice?
- Occupant safety: identifying and correcting vulnerabilities reduces the risk of collapse.
- Protection of the building: correcting weak points limits damage and repairs.
- Informed decision: it allows the owner to understand, before investing, the structural impact of the intervention.
When should the study begin?
As early as possible. The engineers work with the authors of the architectural design, ideally from the concept design (estudo prévio), integrating the analysis into the design decisions. If it is requested at the prior information stage, the owner anticipates the extent of the intervention and, if they decide not to proceed, avoids unnecessary procedures with the municipal councils.
The study requires an understanding of the seismic characteristics of the area, including historical seismic activity, soil properties and applicable standards. See also restoring an old house, from diagnosis to works and the building rehabilitation project.
The cost and timescale of the study depend on the size of the building, the condition of the structure and the information available. For a figure suited to your case, request a proposal.
Frequently asked questions
Who can prepare the study?
Engineers specialising in structural engineering, with specific knowledge of seismic analysis. The architect coordinates the process with the engineer.
Is the study only for licensing?
No. As well as meeting the legal obligation, it shows whether the building needs strengthening and helps to decide the strategy for the intervention.
Do interior-only works also need the study?
They may. If the cost of the intervention exceeds the threshold set out or if there is evident deterioration of the structure, the report is needed, even for works exempt from prior control.