In short
- A change of typology is assessed case by case: it is often an interior alteration exempt from prior control (controlo prévio), but it stops being exempt if it affects the exterior of the building.
- Exempt works must still comply with the technical standards, including habitability standards.
- A bedroom needs direct natural lighting and ventilation and a minimum clear ceiling height of 2.40 m.
- In a T3, the RGEU requires the sanitary facilities to be divided into two spaces with independent access: this is often the critical point.
- The process starts with a survey of the existing situation and moves on to the design, the engineering specialties and notifying the municipal council (Câmara Municipal).
Is it possible to turn a T2 into a T3?
It depends on the property. Any change to the internal layout that alters the typology must comply with the Legal Framework for Urbanisation and Building (Regime Jurídico da Urbanização e da Edificação, RJUE), Decree-Law No. 555/99, as currently in force, and the General Regulation on Urban Buildings (Regulamento Geral das Edificações Urbanas, RGEU).
It is not just one law that has to be complied with: several complement each other, which is why the answers are not always straightforward. There are cases in which it would be physically possible to create the bedroom, but the planning rules or the building itself do not allow it.
It also matters whether the property is legalised and how it was originally approved. If you have doubts about its documentary status, see legalising existing buildings and the technical analysis before buying or intervening.
What procedure is needed with the council?
It depends on what the works change.
- Interior only. Alteration works inside buildings or units are exempt from prior control, provided they do not involve external changes with an impact on the physical or aesthetic characteristics of the building (Article 6 of the RJUE). If the works affect the structure, they require a structural design (projeto de estabilidade) and a statement of responsibility (termo de responsabilidade) from a qualified professional, submitted for filing with the notice of commencement of works.
- Exterior too. If the new bedroom requires opening or altering a window on the façade, or changing the roof, the works become subject to prior control (prior communication (comunicação prévia) or a building permit (licença), depending on the location and the applicable plan).
In either case, the council must be informed of the start of the works, under Article 80-A of the RJUE. It is also advisable to check planning constraints, such as the subdivision permit (alvará de loteamento) or the permitted uses.
See when works are exempt from prior control and how prior communication works.
What does the law require even for interior works?
Exemption from prior control does not remove the obligation to comply with the applicable legal and regulatory standards, including the technical construction standards (Article 6(8) of the RJUE). The habitability rules of the RGEU and the applicable energy performance and accessibility requirements apply, among others. The same is true if the works go from T3 to T2.
Many owners believe that, because interior works do not need a permit, there is no need to comply with the legislation. That is not the case, and this idea puts the works and the investment at risk. The works should start from a design that frames them within the law, prepared by an architect.
What habitability requirements must a T3 meet?
The new bedroom is only habitable if it meets the minimum areas per room, the ceiling height, the lighting and the ventilation. The RGEU provides, for example, for:
- a minimum clear ceiling height of 2.40 m in habitable rooms (Article 65);
- lighting and ventilation through openings directly to the exterior, with a total area of no less than one tenth of the room's area and a minimum of 1.08 m² (Article 71);
- minimum areas for each room and for the dwelling, according to the typology (Articles 66 and 67).
Is the second bathroom the critical point?
Often, yes. In a T2, the RGEU allows the sanitary facilities in a single space. In a T3, the minimum total area is 4.5 m², split between two spaces with independent access: one with a bath or shower tray and washbasin, the other with a WC and washbasin (Article 68).
If that second space has to be created from scratch, it involves new water and drainage connections and ventilation, and it takes up area that has to come out of another room. If the requirements are not met, the extra room cannot be considered a bedroom and the typology does not become T3.
What are the stages of the process?
1. Survey and diagnosis
The first step is an accurate survey of the existing situation: measurements, photographs and analysis of the structure and the services. The technical and planning feasibility, the property's history in the municipal archive and the applicable procedure are assessed. See how an on-site survey is carried out.
2. Architectural design and engineering specialties
Next comes the architectural design, with plans of the existing situation and of the proposal, a design statement (memória descritiva) and a schedule of areas. It is essential to coordinate it with the necessary engineering specialties, such as structural stability, water and drainage, electrical and ventilation. Find out more about engineering specialty projects (projetos de especialidades) and the stages of an architectural project.
3. Municipal council
If the works are exempt, the council is informed of the start of the works and, where there is a structural intervention, receives the structural design and the statement of responsibility for filing. If the works are subject to prior control, the application is submitted through the channels each council provides. See what licensing involves.
4. Works
The Client hires the building contractor directly, based on the quotes requested on the basis of the design. spacelovers is not a building contractor: we provide technical assistance on the Client's behalf, with construction follow-up and checking that the works follow the design. See selecting a building contractor and technical assistance during construction.
What should you watch out for when changing the typology?
It is not always simple. Turning a T2 into a T3 resembles, in some respects, converting commercial premises into housing, where habitability and privacy are critical issues. See how a change of use from commercial to residential works.
If the property has never had three bedrooms, there are few cases in which it is possible, but they exist. In an old apartment, the structure and the services weigh even more in the answer: see renovating an old apartment and apartment renovations. For a broader framework, read about urban rehabilitation and discover the building rehabilitation projects we design.
This content is for information only and does not constitute legal advice. For your specific situation, legal advice should be provided by a qualified professional in the field.
Frequently asked questions
Can I create a bedroom without a window?
No. Habitable rooms must be lit and ventilated through openings directly to the exterior. Without this, the space is not considered a bedroom.
Do I need a building permit to go from T2 to T3?
If the works are interior only and do not alter the exterior of the building, they are, as a rule, exempt from prior control, but the council must be informed of the start of the works. If they affect the façade or the roof, they become subject to prior communication or a building permit.
Who prepares the application for the council?
The architect prepares the design and coordinates the engineering specialties. spacelovers prepares the technical documentation, and the Client contracts the works directly.
Does going to T3 add value to the apartment?
It may influence the value, but there is no guarantee: it depends on the area, the market, the quality of the intervention and whether the new bedroom meets the legal requirements.
How much does it cost to turn a T2 into a T3?
It depends on the property and on what needs to be altered, especially in the structure and the sanitary facilities. For a first order of magnitude, use the renovation cost simulator; for your specific case, request a proposal.
Photo: spacelovers.