In short
- The reference date is 7 August 1951, the date of Decree-Law No. 38 382, which approved the General Regulation on Urban Buildings (Regulamento Geral das Edificações Urbanas, RGEU).
- In some localities, the permit requirement began later, by municipal decision: confirm the date with the municipal council (Câmara Municipal).
- Maintenance works do not change the status of the property.
- Reconstruction, as legally defined, is exempt from the building permit and from prior communication, except for listed buildings or buildings in the process of being listed; extensions and external alterations remain subject to prior control.
- The age of the building is proven with documents, and many municipalities issue a certificate for these properties.
- In REN or RAN areas, what is possible depends on specific regimes and on bodies such as the Regional Coordination and Development Commission (Comissão de Coordenação e Desenvolvimento Regional, CCDR).
What does it mean to be a building constructed before 1951?
The requirement for a building permit became general with the RGEU, approved by Decree-Law No. 38 382 of 7 August 1951. Buildings constructed before then, under the previous law, had neither a building permit nor a use permit.
The Legal Framework for Urbanisation and Building (Regime Jurídico da Urbanização e da Edificação, RJUE) protects these buildings: buildings constructed under the previous law, and their uses, are not affected by subsequent legal and regulatory rules (Article 60(1) of Decree-Law No. 555/99, as currently in force).
What if the property is outside the city?
Outside some urban areas, the RGEU only applied to buildings once the municipal council had decided so for the locality. As a result, the date from which a permit was required may not be 1951. Confirm it with the municipal council of your municipality.
Which works preserve the status of a building constructed before 1951?
Maintenance works do not remove that status. They are exempt from the building permit and from prior communication (Article 6(1)(a) of the RJUE). If they are not exclusively interior works, the municipal council must be informed of the start of the works (Article 80-A).
For other works, the RJUE applies as currently worded, in force since 1 October 2026:
- Reconstruction. This is construction work carried out after the total or partial demolition of an existing building, taking its last valid precedent as the reference, and reconstituting the composition of the facades and the roof (Article 2(c)). The last valid precedent is the last valid and effective urban development operation or the one that, at the time it was carried out, did not require a permit (Article 2(r)). Reconstruction is exempt from the building permit and from prior communication (Article 6(1)(e)).
- Exception: listed buildings. Reconstruction works on listed buildings or buildings in the process of being listed remain subject to a building permit, as do certain works in protection zones (Article 4(2)(d)).
- Extension. If the works increase the footprint, the total gross floor area, the facade height or the height or volume of the building, they constitute an extension and are subject to prior control (Article 2(e)).
- Alteration. Interior alterations that do not touch facades, roofs or heights and do not affect the structure are exempt; external alterations are subject to prior control.
The exemption does not waive compliance with legal and regulatory rules, including municipal plans, easements, public-interest restrictions and heritage protection rules (Article 6(8)). Before going ahead, confirm how your case is framed with the municipal council or with a qualified professional. See also works exempt from prior control and the building permit procedure (licenciamento).
And after the works, how is the building put into use?
Once works carried out under a building permit or prior communication are completed, use is authorised by prior communication to the municipal council, with a statement of responsibility (termo de responsabilidade) (Article 62-A of the RJUE). After exempt works, such as reconstruction, the prior communication with a time limit (comunicação prévia com prazo) applies (Article 62-B), with a statement of responsibility from a professional qualified to author an architecture project.
How do you prove that the building predates 1951?
There is no national rule setting out the proof. Each municipality specifies the documents. The most commonly requested are:
- the land registry certificate (certidão do registo predial) for the property (or a negative certificate, if it is not registered);
- the property tax record (caderneta predial);
- documents proving the standing of the person making the application;
- a location plan;
- photographs of the property;
- in some municipalities, a certificate from the parish council (Junta de Freguesia) on the date of construction.
With these documents, many municipalities issue a certificate of exemption from the use permit for buildings constructed before 7 August 1951. It covers only the original building and presupposes that, after that date, there were no alteration or extension works subject to prior control and no change of use. The documents, time frame and fee are set out in each municipality's rules and fee regulations.
Does a building constructed before 1951 have to comply with current rules?
As long as there are no works, no: buildings constructed under the previous law are not affected by subsequent rules (Article 60(1)).
When there are reconstruction or alteration works, these cannot be refused on the basis of rules that postdate the original construction, provided that they do not create or worsen non-compliance with the rules in force, or that they result in an improvement in safety and health conditions (Article 60(2)). The law may nevertheless require ancillary works to improve safety and health conditions (paragraph 4).
In historic centres and listed areas, interventions must respect the architectural features and the heritage protection rules. See the pages on urban rehabilitation and building rehabilitation, and the article on engineering specialty projects.
What changes if the land is in the REN or the RAN?
The REN and the RAN are public-interest restrictions that appear on the constraints plan (planta de condicionantes) of the municipal master plan (Plano Diretor Municipal, PDM).
- RAN, National Agricultural Reserve: governed by Decree-Law No. 73/2009 of 31 March, as currently in force. Non-agricultural uses of RAN land are exceptional and, when subject to a permit or authorisation, depend on a prior binding opinion from the regional RAN body.
- REN, National Ecological Reserve: governed by Decree-Law No. 166/2008 of 22 August, as currently in force. It covers areas of ecological value and sensitivity or areas exposed to natural hazards.
Before buying, confirm what is actually possible on the land and read the articles on how to buy land and on the municipal master plan.
Which interventions are, as a rule, prohibited in the REN?
In REN areas, the following are, as a rule, prohibited: plot subdivisions (loteamentos), urbanisation works, construction and extension, roads, excavations and landfills, and the destruction of vegetation cover (Article 20(1) of Decree-Law No. 166/2008). The exceptions are uses and actions compatible with the objectives of the REN, listed in Annex II to that decree-law and subject to the conditions of Ministerial Order (Portaria) No. 419/2012 of 20 December. Those that depend on a procedure are subject to prior communication to the territorially competent CCDR.
And the reconstruction of an old house in the REN?
The RJUE exemption for reconstruction does not exclude the REN regime, which applies in parallel. The reconstruction of an existing building in the REN may require it to fit within the compatible uses and actions and a prior communication to the CCDR. Confirm this before demolishing or commissioning a project. On dilapidated buildings, see the article on the declaration of ruin.
How do you go ahead with an intervention in the REN?
- Check the PDM constraints plan, to find out whether the property is in the REN and in which type of area.
- Check whether the proposal fits within the compatible uses and actions in Annex II to the REN regime.
- Submit the prior communication to the CCDR, when required, with the documents listed in Ministerial Order No. 419/2012. The CCDR decides; in some cases, the Portuguese Environment Agency (Agência Portuguesa do Ambiente) issues a binding opinion.
- Follow, in parallel, the planning procedure with the municipal council.
- Comply with the conditions imposed.
The time frames depend on several bodies. Occupations without a permit may give rise to sanction proceedings and to the restoration of the previous situation.
Can I buy a pre-1951 property without a use licence?
You can, but with care. When buying buildings or units (frações), the transfer document must state the planning permit, the declaration that it exists or the declaration that it does not exist, failing which the deed is voidable (Article 4-A(14) of the RJUE). For a pre-1951 property, ask the seller for the municipality's certificate of exemption, where one exists, and compare what is built with what is recorded in the municipal planning file.
After the original construction, works may have been carried out that required a permit and were never regularised, such as lean-to roofs, annexes, swimming pools or new openings. These situations may have consequences for the new owner.
Before buying:
- ask for the municipal planning file and compare it with what exists on site;
- check the footprint, the number of storeys and whether there are annexes;
- confirm the works carried out in the meantime;
- ask an architect to compare what has been built with what is documented.
If you find structures that are not shown in the documents, see the article on legalising existing buildings.
spacelovers is an architecture studio that designs, obtains permits and provides technical assistance during construction. For an old property, we analyse the regulatory framework and prepare the project; decisions and contracts belong to the Client.
Frequently asked questions
Can the municipal council issue a certificate if there is no project on file for my building?
It is for these cases that many municipalities issue the certificate of exemption from the use permit for buildings constructed before 1951. The requirements and documents depend on the municipality.
Does an extension carried out many years ago remove the pre-1951 status?
The certificate covers only the original building. Later extensions or alterations that were subject to prior control must have their own permit; if they do not, they may need to be legalised.
Do I need a building permit to reconstruct an old house?
Since 1 October 2026, reconstruction based on the last valid precedent has been exempt from the building permit and from prior communication, except for listed buildings or buildings in the process of being listed. If it increases the floor area, height or volume, it is an extension and requires prior control. In REN or RAN areas, those regimes also apply.
Can I reconstruct an old house in the REN?
It depends on the type of REN area, on whether it fits within the compatible uses and actions of the REN regime and Ministerial Order No. 419/2012, and on the decision of the competent bodies. Check the specific case before buying or investing in a project.
This content is for information only and does not constitute legal advice. For your specific situation, legal advice should be provided by a qualified professional in the field.