Preliminary design brief for an architectural project.
The stage in which we define what the works have to resolve: needs, budget and constraints, before any drawing.

In 30 seconds
- The preliminary design brief is the first stage of an architectural project, before any drawing.
- It brings together the needs, the available budget and the constraints of the site and the law.
- It results in a brief (spaces, areas and priorities), prepared with the Client, and a first reading of feasibility, which is neither an approval nor an opinion from the municipality (Câmara Municipal).
- It reduces the risk of designing a solution that later does not fit the budget or is not permitted.
This is the stage that lays the foundations for all the others. Deciding early what the works have to resolve reduces the risk of redoing drawings later.
02 — What it includes
Three questions, one clear answer.
We talk with you, visit the site and gather what the project will need.
Needs
- Who will use the space, and how
- Spaces needed and approximate areas
- What is essential and what is desirable
- Relationships between spaces, light, privacy and storage
Budget
- Funds available for the design and for the works
- Allowance for unforeseen costs, furniture and equipment
- Whether the works are carried out in one go or in stages
- Balancing ambition and budget
Constraints
- Location, orientation and condition of the property or plot
- Municipal master plan (PDM), administrative easements and public-interest restrictions
- The regime that applies to the works: exempt, prior communication (comunicação prévia) or building permit, to be confirmed case by case
- Deed establishing the horizontal property regime (título constitutivo da propriedade horizontal) and the condominium regulations, where applicable
With these three elements, we make a first reading: does what you want appear to fit within the budget and the law? Which stages and services should be contracted? It is a first reading: it does not replace the municipality's assessment, nor does it guarantee approval.
03 — What you receive
Deliverables at this stage.
- Preliminary design briefA document that sets out the needs, the areas and the priorities.
- First feasibility assessmentAn indicative reading of what is possible given the budget, the site and the law. It does not replace the municipality's assessment.
- Recommended stages and servicesSet out in the proposal, depending on the works.
Documents to gather
- Urban property tax record (caderneta predial urbana)
- Land registry certificate (certidão permanente)
- Licence, use authorisation or other title of use, and the housing technical file (ficha técnica da habitação), if they exist
- Existing plans and design for the property (including as-built drawings), if they exist
- Deed establishing the horizontal property regime and the condominium regulations, where applicable
- Topographic survey, for a plot of land
An indicative list; we confirm case by case which are needed. If you do not have any of these documents, we explain how to obtain it.
04 — What you decide
The decisions that are yours.
- The spaces and uses the design has to resolve.
- What is essential and what can wait.
- The maximum budget and how it is split between design, works and equipment.
- Whether the works go ahead in one go or in stages.
- Whether it is worth submitting a pre-application enquiry (PIP) to the municipality before moving forward.
- The design stages to contract.
05 — Common mistakes
Common mistakes, and how to avoid them.
How to avoid it. Set a realistic maximum figure before the concept design. The brief and the budget are adjusted to each other.
How to avoid it. Separate what is indispensable from what is desirable. That list is what makes it possible to decide when the budget gets tight.
How to avoid it. Whether the works are exempt, subject to prior communication or to a building permit depends on what is done, where, and in which property. We confirm it at the very start.
How to avoid it. Gather the property's documents and the condominium rules, where applicable, before finalising the brief.
Client testimonials
What our Clients say.
Google reviews from our Clients
Client reviews on Google
A selection of published reviews, shown as in the original. See all reviews on Google (4.8 · 47 reviews) ↗
07 — How we work
We think before we build.
This stage corresponds to the first contact and the proposal.
- 1. First contactOnline meeting and questionnaire.
- 2. ProposalSent by email, with the scope and the fees by stage.
- 3. Concept design and designSent by email and presented in a meeting.
- 4. Building permitThe applicable procedure is handled by the studio, where required.
- 5. WorksThe Client hires the building contractor directly. The studio provides technical follow-up of the works.
- 6. HandoverFinal site visit with the Client and handover of the keys.
08 — Frequently asked questions
About this stage.
What is the preliminary design brief?
It is the first stage of an architectural project. It brings together the needs, the budget and the constraints of the site and the law, and sets out what the design has to resolve.
Do I need a preliminary design brief if I already know what I want?
It is advisable. Even with clear ideas, the brief checks, as a first reading, whether they fit within the budget and the law, and records the priorities for the following stages. In small works, it can be simpler.
What information should I prepare?
The needs of those who will use the space, the available budget and the property's documents. The list on this page is indicative; we confirm case by case.
What is the difference between the preliminary design brief and the concept design?
The preliminary design brief defines what needs to be resolved. The concept design presents the possible solutions, in sketches and schematic plans.
Can I contract this stage only?
You can. The stages to contract depend on the works. We state in the proposal which ones apply to your case.
How much does a preliminary design brief cost and how long does it take?
It depends on the size and complexity of the project and the time that decisions take. Contact us for a spacelovers proposal, with the schedule and the fees by stage.
Sources and note
- Portaria no. 701-H/2008, of 29 July (content of the programmes and designs for public works, where it is mandatory; used as a reference for good practice in private works)
- Regime Jurídico da Urbanização e da Edificação (RJUE, Legal Regime for Urbanisation and Building), Decree-Law no. 555/99, of 16 December, as currently in force, for the regime that applies to each building project
This page is for information only and does not replace the analysis of each case, nor does it constitute legal advice. The specific framework that applies to a building project depends on the property, its location, the territorial management instruments and the applicable municipal regulations. The planning regime was amended in 2024 (Decree-Law no. 10/2024, of 8 January); the regime in force is confirmed in each case.
See also: Building permit · Prior communication · Pre-application enquiry (PIP) · Works exempt from prior control